The City of Hailey received an $84,000 grant from ITD to install additional sidewalks along Elm St. to provide safe walking areas for Hailey Elementary School students. Final designs are being prepared with construction expected this summer.
The developer of the Sweetwater Project agreed to pay for the installation fo a traffic signal at Countryside Blvd. and Highway 75. The equipment--poles and lights--have been ordered. Final specifications and drawings are being reviewed by ITD. Bidding is expected in May with construction occurring this summer.
The City of Hailey has purchased two sets of in-road pedestrian crossing light systems. These systems provide flashing LED lights to alert drivers of pedestrians crossing the streets. The new systems will be installed on Main St. at the Croy St. and Myrtle St intersections. See www.xwalk.com and www.crosswalks.com for more information on these systems.